Construction Africa and Middle East
|
CONSTRUCTION
AFRICA |
|
MARINE |
|
MIDDLE EAST |
|
TOTAL |
|
R MILLIONS* |
2012 |
|
2011 |
|
2012 |
|
2011 |
|
2012 |
|
2011 |
|
2012 |
|
2011 |
|
Revenue* |
5 848 |
|
5 597 |
|
903 |
|
1 031 |
|
1 357 |
|
2 480 |
|
8 108 |
|
9 108 |
|
Operating profit/(loss)* |
321 |
|
(653) |
|
(1 184) |
|
(582) |
|
(454) |
|
(164) |
|
(1 317) |
|
(1 399) |
|
Ongoing construction activities* |
69 |
|
237 |
|
(1 184) |
|
(582) |
|
(67) |
|
|
|
(1 182) |
|
(345) |
|
PPP Investments and Services* |
252 |
|
260 |
|
|
|
|
|
|
|
|
|
252 |
|
260 |
|
Competition Commission penalties/Gautrain* |
|
|
(1 150) |
|
|
|
|
|
|
|
|
|
|
|
(1 150) |
|
Additional contract completion and impairments* |
|
|
|
|
|
|
|
|
(387) |
|
(164) |
|
(387) |
|
(164) |
|
Segment assets* |
3 447 |
|
2 926 |
|
658 |
|
358 |
|
1 578 |
|
1 605 |
|
5 683 |
|
4 889 |
|
People |
7 393 |
|
8 891 |
|
131 |
|
511 |
|
199 |
|
318 |
|
7 723 |
|
9 720 |
|
LTIFR (Fatalities) |
1.0 (0) |
|
1.6 (1) |
|
0.6 (0) |
|
4.2 (0) |
|
0.5 (0) |
|
0.3 (0) |
|
0.7 (0) |
|
0.9 (1) |
|
Order Book* |
7 163 |
|
6 929 |
|
178 |
|
606 |
|
1 654 |
|
2 430 |
|
8 995 |
|
9 965 |
|
|
JEROME GOVENDER
OPERATING PLATFORM EXECUTIVE |
|
CONSTRUCTION AFRICA AND MIDDLE EAST
A KEY ACHIEVEMENT WAS
THE AMALGAMATION OF
THE CONSTRUCTION BUSINESSES
INTO A UNIFIED PLATFORM.
THIS INTEGRATION IS ALREADY
PAYING DIVIDENDS IN TERMS OF
GREATER SYNERGIES, SHARING
OF EXPERTISE AND MARKET
KNOWLEDGE AS WELL
AS COST SAVINGS. |
|
Some solid performances in extremely trying conditions were entirely
overshadowed by the substantial losses sustained on the Gorgon
Pioneer Materials Offloading Facility (“GPMOF”) at Barrow Island,
Australia, and a disappointing performance by the Middle East.
LEADERSHIP
Several key executive appointments were made in order to
strengthen the platform and its various entities. Jerome Govender
was appointed as the new platform executive. Jerome has been
the managing director (“MD”) of Bombela Concession Company
since 2007, having joined Murray & Roberts in 2002. Chris Botha,
previously MD of Concor Roads & Earthworks, was appointed chief
operating officer overseeing the civils companies and Gavin Taylor
was recruited from VINCI Construction UK to become the chief
operating officer heading up the Building and Africa operations.
Mark Andrews was appointed MD Middle East, Cobus Snyman
was promoted to the position of MD Concor Roads and Earthworks
and Alex Boyazoglu was appointed MD of Buildings. Andy Fanton
assumed the position of MD Marine and Dave Heron was named
MD Western Cape, with Mark Johnston focusing on Namibia.
PERFORMANCE
Losses sustained on fulfilling Marine’s contractual GPMOF obligations
amounted to some R1,2 billion this year while the Middle East
recorded a loss of R454 million.
The Group’s commitments on GPMOF were discharged, although
later and at a greater cost than had been anticipated. Similarly in the
Middle East, cost overruns on projects largely completed in previous
years, were accounted for this year.
There were positive developments on realising uncertified revenue
claims relating to GPMOF. While there was little progress on
arbitration of the Dubai International Airport claim, we are optimistic
that this will be settled in our favour while remaining open to the
possibility of reaching an amicable settlement.
Within the South African civil engineering and construction sectors,
conditions remained challenging and margins were extremely low.
Concor Opencast Mining recorded an overall satisfactory performance
but challenges experienced at a single project caused it to post a net
loss of R27 million.
Building work disappointed with orders falling well short of budget,
most notably in Gauteng.
Positives for the year were solid performances by Murray & Roberts
Botswana, Concor Civils and Concor Roads & Earthworks.
During the year the St Regis resort development in Abu Dhabi was
delivered on time and to widespread acclaim. In the Western Cape,
the Aurecon office development became the first local building to be
awarded a Green Building Council of South Africa five-star green
rating, its construction boosting Murray & Roberts’ green building
credentials and expertise. Also in the Western Cape, the awarding
of the high-rise Portside building to Murray & Roberts Western Cape
was a notable highlight.
On the power project the value of the Medupi civils contract grew
exponentially to over R8 billion.
* |
Excludes losses from Gautrain/Competition Commission penalties Rnil (2011: R1 150 million; 2010: R619 million), Middle East R387 million (2011: R164 million; 2010: R89 million) and GPMOF of R1 189 million (2011: R582 million; 2010: Rnil). |
A resolution of all major commercial issues with Eskom relating to the
civil engineering contract at the Medupi power station was reached
during the year. The agreement settled all commercial disputes
on the project to date, with the remaining R3,0 billion of civils work
on this project carrying no more than normal construction risks at
acceptable margins.
The platform did not suffer any fatalities during the year and
the lost time injury frequency rate (“LTIFR”) improved slightly
from 0.90 to 0.71.
Operating loss for the platform was R1,3 billion (2011: R1,4 billion)
on turnover of R8,1 billion – which represents a 11% decline on the
previous year. Excluding losses on GPMOF and in the Middle East,
the platform returned a small profit.
MURRAY & ROBERTS MIDDLE EAST
In a most challenging year, the company had to account for losses
on projects that had either been completed in previous years or
which were substantially completed this year. This was because the
costs involved in seeing these projects through to completion and the
defects liability periods were found to have been underestimated.
At the same time the construction sector in Abu Dhabi ground to a
virtual standstill. This was after the company had ended the previous
year with serious prospects of securing work worth at least R5 billion
in the following year, none of which materialised. After construction
activity in Dubai collapsed in 2008, the Abu Dhabi standstill highlighted
the company’s over-reliance on UAE capital.
The net result of these developments was that stated revenue for
the year was less than half of that budgeted for, and a net loss of
R454 million was incurred. The only major contract being executed
at year-end was the R6,5 billion Mafraq Hospital for the Abu Dhabi
health authority. Arbitration of Murray & Roberts Middle East’s
claims relating to the Dubai International Airport work, completed
in 2008, was suspended earlier this year. This was after an issue
around the identity of the contracting entity within the Dubai
Government was disputed. Despite this, efforts continue to reach
an amicable settlement.
Developments this year also revealed Murray & Roberts Middle East’s
over-reliance on its relationship with joint-venture partner, the
Al Habtoor Leighton group. A significant investment is now being
made by the company in Qatar where work ahead of that country’s
hosting of the 2022 FIFA World Cup™ is expected to begin in earnest
in FY2013. In Qatar, Murray & Roberts Middle East has established
a local joint-venture company but will retain management control.
The company performed well on safety, achieving a LTIFR rate
of 0.53, better than other parts of the Group. Senior HSE
managers with responsibility and the authority to ensure
compliance with Murray & Roberts systems and standards
are appointed to all projects.
Work opportunities will be followed up in various North African and
Middle East countries and even some in the Far East where the
company’s expertise translates into reasonable prospects of securing
and executing work at acceptable margins. Such opportunities could
include, in addition to the Middle East’s traditional building projects,
civils and roads work and will not be restricted to the company’s
typical profile of only working on so-called mega projects.
Prospects at the end of the year were at least as good as those at
the same time a year previously, with several projects, notably in
Qatar, expected to be announced shortly.
CONCOR CIVILS
Concor Civils returned satisfactory operational, financial and safety
performances this year.
The Eskom power generation work runs until 2015, ensuring a
secured income stream. A major achievement this year was the
settling of all outstanding commercial issues relating to work at
Medupi, a landmark development that will have lasting benefit for
the Group. The successful Ngqura Container Terminal contract has
grown significantly in scope, and will continue in FY2013.
The impact of lower margins, experienced on a majority of projects,
was offset by an excellent performance on the Medupi chimneys and
Coega contracts.
Excluding Medupi, revenue rose by a third over the previous year.
However, a notable trend is that whereas in the past most work was
sourced from the mining sector, today Concor Civils is
overwhelmingly dependant on public-sector projects, which carries
some risk. Opportunities in the private sector remain scarce and
several of those awarded to our competitors were undertaken at
unsustainable prices.
In the immediate future Concor Civils will remain focused on power
generation, water and waste water treatment. There are however
significant opportunities in mining, including opportunities in Zambia
and Mozambique. In addition to traditional coal-fired energy, Concor
Civils is well positioned to secure work in the fields of wind and solar
power. An increased focus in the short term will be on concrete
repair, a market in which Concor Civils currently has no presence but
which has the potential to contribute to turnover with good margins.
Safety performance was satisfactory, with no lost time injuries being
reported at Coega, Kusile or the Zeekoegat Waste Water Treatment
Works. A LTIFR for the year of 1.23 was commendable.
CONCOR ROADS & EARTHWORKS
The division performed satisfactorily this year, posting pleasing
turnover and profits in a depressed market.
Public sector projects remained few and far between with no large
contracts being put out to tender and the impasse over urban tolling
casting a pall over the sector. At the same time, private sector
spending slowed significantly. The bitumen shortage impacted
negatively on road construction work and fierce competition
translated into pressure on margins, raising the risk profile of several
projects. Mining infrastructure contracts continued to deliver better
than expected.
Towards the end of the reporting period there were indications of an
upturn in public sector spending with a healthy order book reflecting
a 40% rise in projected turnover for FY2013. Almost half of this
budgeted income however, will be derived from South African road
contracts where margins remain tight. An increasing proportion of
next year’s work is expected to come from the rest of Africa, an area
which remains buoyant and very promising.
Concor Roads & Earthworks performed well on a number of
non-financial indicators, notably on human resource development.
Seventeen bursaries and 56 learnerships were awarded this year.
Two employees were enrolled for BCom degrees in operational risk
management. Performance on enterprise development was
particularly pleasing with no fewer than 18 initiatives being supported
within the platform during the year. On safety the business is driving
towards a 0.5 LTIFR using the 1 million hour benchmark.
MURRAY & ROBERTS BUILDINGS
Market conditions continued to be extremely difficult this year with
limited opportunities becoming available and Murray & Roberts
Buildings succeeding in securing only a small proportion of these.
Several tendered and negotiated opportunities envisaged at the
beginning of the year failed to materialise. These included a number of
projects for which Murray & Roberts Buildings had been identified as
the preferred contractor. Two significant loss-making projects in the
petrochemicals sector impacted negatively on the division.
On a more positive note however, several key projects were
completed in the year for premium clients whose satisfaction has
already translated into the successful award of new work.
While revenue was 36% down on budget, towards the end of the
financial year, two important projects worth more than R650 million
were secured. In addition, it is expected that key negotiated projects
will materialise in the first half of the new financial year. Business won
towards the end of the year was furthermore at improved rates relative
to those achieved earlier in the year, giving further reason for guarded
optimism. Towards the end of the year, recruitment of talented staff
began in earnest, in anticipation of an upturn in orders.
One response to the constrained market conditions of recent years
has been to seek and execute work in geographic areas in which
Murray & Roberts Buildings has not recently operated. This is
expected to have the effect of diversifying the division’s risk and
revenue sources. In addition to operating in more outlying areas
within South Africa, opportunities in neighbouring states are being
actively pursued.
Murray & Roberts Buildings’ LTIFR was 0.73 which is in line with the
Group standard of less than 1.
MURRAY & ROBERTS MARINE
Following the large losses sustained on the GPMOF in Western
Australia, a new management team, headed by Andrew Fanton, was
appointed at Murray & Roberts Marine in late 2011. Subsequently the
company was restructured to support its engineering, procurement
and construction (“EPC”) focus and to support the goal of doubling
its size within three years to a R1 billion business. Apart from
organisational restructuring, new business processes were put in
place while a project control department, focused on providing
management with detailed and dynamic project information, was
established.
To achieve the objective of doubling turnover, Murray & Roberts
Marine will prioritise Southeast Asia and West and East Africa.
A dedicated office headed by a general manager was established
in Kuala Lumpur and relationships in key markets will be either
established or cemented, in some cases leveraging off the local
presence of other members of the Construction platform. While there
are few prospects within South Africa, considerable opportunity, from
a variety of customers and sectors, is seen in the new target markets
as well as in the traditional markets of Australia and the Middle East.
A key future focus will be on forging joint-venture partnerships with
companies that have proven resources and expertise in marine work
which complements the EPC strengths of Murray & Roberts Marine.
In FY2012 a dedicated safety, health, environment and quality team
was established. This team will be tasked with developing detailed
safety, health, environmental and quality (“SHEQ”) protocols and
reporting matrixes for the company.
The company’s financial performance in the past year was
disappointing, with only 50% of budgeted revenue being achieved.
This was largely ascribable to the deferral or even cancellation of
several tenders. Excluding GPMOF, gross profit margins remained
healthy. Management remains extremely focused on vigorously
pursuing a substantial GPMOF commercial recovery schedule.
Towards the end of the year, the arbitration process ruled in favour
of Murray & Roberts Marine’s position on Change Order 18.
At year-end, only 25% of the budgeted order book had been
secured. However, bids for six projects with a total value of
R2,5 billion and due to commence in FY2013 had been or were in
the process of being submitted.
CONCOR OPENCAST MINING
The business continued to experience strong growth but returned a
disappointing profit. This was the result of challenges experienced at
a single project, without which Concor Opencast Mining would have
recorded a satisfactory profit.
Overall performance on safety improved from the previous year,
however several injuries contributed to an LTIFR of 1.72 compared to
2.02 the year previously. The division has prioritised safety in line with
Group policy and its own commitment to keeping employees and
subcontractors safe. While strong growth potential exists both within
South Africa and, especially, elsewhere in southern Africa (for coal,
platinum, diamonds, copper and uranium projects), the business has
done little to market itself. This will be rectified as Concor Opencast
Mining positions itself to achieve revenue of R1 billion by 2015.
Another key objective will be to reduce the company’s dependence
on South African platinum, a sector which is experiencing welldocumented
stresses at present.
Management depth and access to market intelligence will be
bolstered in the new year to enable Concor Opencast Mining to
realise its ambitious expansion plans. At year-end the order book
showed a substantial increase on FY2011.
MURRAY & ROBERTS NAMIBIA
Dramatically increased competition resulted in a disappointing
performance by Murray & Roberts Namibia after the record
achievements of 2011.
The operation only achieved breakeven but the outlook for FY2013 is
considerably more promising. Material risks include the heightened
level of competition, especially from Chinese contractors, with
resulting pressure on margins.
While there is much expectation around uranium investment and an
upswing in civil engineering work, the bulk of Murray & Roberts
Namibia’s income in the near term is likely to be derived from the
building sector, where there are some promising prospects.
MURRAY & ROBERTS WESTERN CAPE
The regional market remained flat, even deteriorating during the year
with calls for tender declining by some 50%.
A major breakthrough for Murray & Roberts Western Cape was
winning the tender to build FirstRand and Old Mutual’s landmark
Portside building in the Cape Town CBD. This boosted turnover
by 50% over projections and resulted in a small operating profit.
The budgeted order book for the next year was 90% secured at
the end of the year. However, margins remain extremely low and,
at about 2.9%, are expected to be at around the same levels
recorded in FY2012.
THE FUTURE: SOME CONCRETE FACTS
Concrete is not what it used to be – not since Murray & Roberts scientists set about changing almost everything we all thought we knew about this basic building material.
The strength of concrete is measured in megapascals (MPa). In
theory, a cubic metre of concrete that is rated 30 MPa (a typical
standard for structural concrete) is able to withstand the weight of
six bull elephants.
Traditionally, 30 MPa concrete requires between 300 kg and 350 kg
of ordinary cement per cubic metre. But now scientists working for
Murray & Roberts have developed a technology that meets the
30 MPa standard using just 25 kg of cement or even less. Not only
does it meet the standard, it far exceeds it. To date strengths of up
to 52 MPa have been achieved using Murray & Roberts’ patented
ARC (“Advanced Recrystallisation”) technology and only 25 kg of
cement per cubic metre.
Best of all, the ARC process uses large amounts of recycled waste
products. The most common recycled ingredient is slag from the
steel manufacturing process. However, at the 102 Rivonia Road
project, now under construction in Johannesburg, Murray & Roberts
Buildings is using up to 64% fly ash, a recycled by-product from
coal-burning power stations for which there is usually no use.
Research scientist and head of Murray & Roberts’ Concrete Centre
for Excellence, Cyril Attwell, says: “Not only does the process
require less ordinary cement and is environmentally friendly, but
also, because the concrete can gain higher strengths, we can build
faster; sometimes a lot faster.”
Cyril, whose official job title is Group Concrete and Research
Manager, adds that the typical specification for waste water
treatment plants requires concrete that uses 420 kg of binder per
cubic metre. His team of scientists has now developed techniques
that can meet the specification but use only 330 kg. “This gives a
distinct cost saving advantage to our clients.”
Cyril and his two colleagues at the Concrete Centre for Excellence
in Amalgam on the West Rand, Warren McKenzie (Group Concrete
Technologist) and Andries Magale (Laboratory Technician) have
developed some remarkable concrete technologies, several of
which are world firsts. Just one is a smart concrete involving the
introduction of a particular type of bacteria into the mix. “Under
certain conditions of chemical attack, which are usually bad for the
concrete, these bacteria thrive, reproducing rapidly and consuming
the chemicals that attack the concrete. In addition, as they eat
up the threat, the bacteria defecate calcrete. These deposits fill
up cracks that would normally weaken the structure.”
The team is also investigating an ingenious electrochemical system
that makes marine concrete more resilient to both wave action and
chemical degradation. The system draws carbon dioxide from the
sea water, encouraging the growth of a layer of coral that protects
the undersea concrete. Such is the effectiveness of the coral that
the concrete does not have to be treated with expensive chemicals
– and it is almost completely maintenance free.
In 2010 Murray & Roberts’ southern Africa operations used some
1,8 million tonnes of concrete. The benefits derived from the
advances being pioneered by Cyril and his colleagues are
significant. For example, through the use of ARC processes, cement
consumption on the Gautrain Rapid Rail Link was cut by about
110 000 tonnes.
However, such benefits are not just measured in monetary terms.
Cape Town’s Portside development, Cyril believes, will be the first
building project to receive a full three-star Green Star eco-friendly
rating for construction materials. The concrete being poured
contains up to 70% waste materials and as much as 10% of
the aggregates consumed (typically sand and stone) are
waste materials.
“Recently the consulting engineer working on Portside asked us
to supply even more waste material because it just makes such a
strong concrete,” says Cyril. “This technology means we can save
money and time, deliver a superior result and at the same time,
do our bit to save the environment.” |
|
Controlling costs remains a key management concern in an exceptionally
low-margin environment. There has been no significant increase in
overheads since the restructuring exercise carried out in 2010.
MURRAY & ROBERTS BOTSWANA
A satisfactory year saw revenue approach the R500 million mark
(a 34% increase on the previous year) while the operation also
performed well on profit and cash generation.
At 0.8 Murray & Roberts Botswana’s LTIFR was largely unchanged
from FY2011. Tragically, one employee, supervisor Gosekamang
Kheru, was killed by lightning while working at De Beers’ Jwaneng
Diamond Mine where the business is raising the walls of a slimes dam.
Significant work undertaken during the year included the Rail Park
Shopping Mall for key clients where Eris Properties is a shareholder,
FNB’s Gaborone office block for Eris Properties and various
construction projects for De Beers including the first phase of the
two-tower i-Towers development for City Skypes, Botswana’s tallest
buildings.
With R300 million of the order book secured at year-end and another
R100 million at an advanced stage of negotiation, all indications are
that FY2013 will be a record year for the business. Driving this will
be an expected upsurge in office building in the Gaborone CBD.
However, building activity in the capital is expected to slow down
in FY2014.
To offset this, management of Murray & Roberts Botswana intend
targeting civils and infrastructure work for the country’s booming
mining and minerals sector. This is expected to mean that, whereas
80% of revenue is currently generated from building work and 20%
from civil and related contracts, in future the mix may be in the region
of 70/30 in favour of the latter. In the new year, opportunities in
Zambia will also be explored.
MURRAY & ROBERTS PLANT
This division provides plant and equipment to the Civils Construction
and Building Africa businesses. The business has successfully
concluded the merging of the old Concor Plant and Murray & Roberts
Plant and Equipment businesses.
With a turnover exceeding R400 million, the division’s spread of
internal clients ensured that Murray & Roberts Plant had the best
utilisation rates and the most superior technical backup service in
its sector. The business was also comfortably ahead of its peers
in terms of the safety of the plant and equipment it supplies.
An initiative launched last year was the creation of a special cost
code for safety. In this way it should be possible to measure the
direct financial costs involved in supplying, maintaining and operating
safe plant and equipment.
TOLCON GROUP
The Tolcon Group performed to expectations in the past year,
securing the tolling operations-and-maintenance contracts for
the N1 North, the N2 South (Oribi) and the N17 (Leandra plaza).
Tolcon and the rest of the tolling industry face various challenges
including mooted changes to labour legislation, more onerous
contracting terms, high labour turnover and increased competition
resulting from the advent of several new entrants to the market.
ISO 9001 quality accreditation with regard to toll collection processes
was achieved by Tolcon Lehumo and PT Operational Services.
With its extensive portfolio now bedded down, the Tolcon Group is
well positioned to explore additional opportunities within the transport
infrastructure management arena.
MURRAY & ROBERTS CONCESSIONS
The Group’s 33% investment in Bombela Concession Company
performed well with the service enjoying growing support from the
travelling public and the Rosebank Station to Park Station link being
successfully opened during the year. By the end of June 2012
passenger numbers had reached 800 000 per month, 65% growth in
patronage in the 11 months since the Tswane-Rosebank service was
opened. Arbitration rulings relating to water ingress and the Group’s
delay and disruption claims are expected by the end of calendar year
2013, and calendar year 2014 respectively.
Entilini Concessions responsible for the operations at Chapman’s
Peak attracted negative attention over local concerns about the visual
impact of the toll plaza, now under construction. Legal challenges
failed however and work is on schedule for completion in the second
quarter of FY2013.
Murray & Roberts Concessions is the designated standby bidder on
the N1/N2 Winelands toll route but no decision has been taken on
awarding this contract. The R300 route redevelopment, for which the
Group was the scheme developer, has yet to be put out to tender.
Similarly no decision has been taken on public-private partnership
bids to build and operate prisons. The Request for Quotation (“RFQ”)
to build, finance and operate the long-awaited upgrade of Chris Hani
Baragwanath Hospital is eagerly anticipated.
PROSPECTS
The significant losses incurred on the GPMOF Project and in the
Middle East have now been taken to book, allowing the platform to
focus strongly in the new year on its continuing recovery. Measures
are in place to accelerate this process and to prepare for growth,
including stabilising operations, securing a quality order book and
strengthening risk management processes.
Proceeds from the large-project claims processes are unlikely to
provide a significant windfall during the new financial year but the
process of pursuing these claims will be prioritised by the platform
leadership.
At year-end almost 75% of budgeted order book had been secured
– a satisfactory achievement – but at margins that were generally
lower than those secured a year previously. The Buildings business
(which recorded a number of pleasing project wins late in the year)
will explore creative methods of engaging with clients to achieve
solutions that will address the historically low margins achievable on
most projects.
Co-operation between Buildings businesses within the platform
will be emphasised to exploit opportunities.
Across the platform, rail and oil & gas have been identified as
particularly promising growth opportunities while the business is
increasingly positioning itself as a leader in environmentally-friendly
building solutions.
In the Middle East opportunities in Qatar ahead of that country’s
hosting of the 2022 FIFA World Cup™ will be explored with new
joint-venture partners as will opportunities in other markets within
the region.
The platform’s expansion into sub-Saharan Africa will be accelerated,
building on the strength of the Murray & Roberts brand, particularly in
the SADC region. Closer liaison with other Group platforms will be
prioritised.
Management will lead various safety initiatives in the new year
including Visible Felt Leadership.
|